ITEM |
WORK DESCRIPTION |
CLIENT / MAIN CONTRACTOR |
AMOUNT RM |
YEAR |
01 |
To supply & fabricate of 2 units Acoustic
Canopies for Cat. 3516TA and Cat. 3512B DITA for project of
CAKERAWALA GAS |
TRACTORS MALAYSIA (1983) Sdn Bhd |
238,000.00 |
2000 |
02 |
To supply, installation & testing of Acoustic
Equipment for Generator rooms at Telekom Exhanger |
TELEKOM MALAYSIA |
100,600.00 |
2000 |
03 |
HOTEL PROJECT, Steam Boiler Installation
Works at hotel Equatorial Melala |
MECHMAR |
360,000.00 |
1998 |
04 |
MEGASTEEL PROJECT, Steam Boiler Installation
Works At Megasteel, Banting |
MECHMAR |
290,000.00 |
1998 |
05 |
TRACTORS ENGRG COMPLEX, Mechanical
Installation Works For The Gas Turbine Co-Generation Plant at
Puchong |
TRACTORS M'SIA (1982) S/B |
310,460.00 |
1998 |
06 |
TELEKOM JLN. RAJA CHULAN, Mechanical
Installation For New Engine Driven Genset (3x1000kva) |
TRACTORS M'SIA (1982) S/B |
110,000.00 |
1998 |
07 |
TNB - KLANG, Dismantling & Installation
of D398 Genset, Trailer, Radiator. |
TRACTORS M'SIA (1982) S/B |
256,000.00 |
1997 |
08 |
HOTEL PROJECT, Steam boiler, calorifier
& piping installation for Equatorial Hotel in Cameron Highlands |
GEROGE KENT |
350,000.00 |
1997 |
09 |
GUTHRIE PROJECT, Thermal oil heat &
piping installation for Guthrie Medicare in Senawang. |
MECHMAR |
80,000.00 |
1997 |
10 |
KLCC PROJECT, Stand-by Generator set
installation for KLCC Project. |
TRACTORS M'sia (1982) |
180,000.00 |
1997 |
11 |
TOC PUBLIC BANK, Mechanical Installation
of 2 units Turbine Generator set at Bangi. |
TRACTORS M'sia (1982) S/B |
460,950,00 |
1996 |
|